Wednesday, March 12, 2025, 6:13PM |  64°
MENU
Advertisement
A contractor is on a lift, to the right, as the back of a house is demolished first, below the landslide on Route 30 and near Electric Avenue on Friday in North Braddock. The demolition crew was trying to spare the warehouse below from the damaging debris.
3
MORE

PennDOT awards contract to rebuild Route 30 in East Pittsburgh

Darrell Sapp/Post-Gazette

PennDOT awards contract to rebuild Route 30 in East Pittsburgh

Now the emphasis has shifted to rebuilding Route 30 in East Pittsburgh.

Golden Triangle Construction of Imperial received an immediate notice Friday to proceed with the project after the Pennsylvania Department of Transportation awarded the firm a $6.54 million emergency contract. The goal is to install a 400-foot-long, 20-foot-tall retaining wall and rebuild more than 500 feet of the highway by the end of June.

Crews have been working since April 7 to stabilize the hillside between Route 30 above and Electric Avenue below. That’s when three lanes of the highway fell about 30 feet down the hillside, provoking a landslide that damaged a house and two of the five buildings of the Electric Avenue Apartments so severely that they had to be razed.

Advertisement

Earlier this week, PennDOT District 11 Executive Cheryl Moon-Sirianni said consultant Gannett Fleming Inc. went out of its way to design the project with the easiest, most efficient construction methods to complete the project safely. That included checking with suppliers to make sure they could provide precast concrete panels and fabricated steel rods for the wall to meet the accelerated schedule.

An aerial view of the Route 30 landslide in East Pittsburgh toward Electric Avenue on April 10.
Ed Blazina
Federal agency to reimburse state $9 million for Route 30 emergency repairs

“We know how important this highway is,” she said then.

The highway, which carries 25,000 to 30,000 vehicles daily, is a major artery to the Parkway East from North Versailles, East McKeesport and North Huntingdon. It is closed between the outbound East Pittsburgh exit and the Westinghouse Bridge.

PennDOT officials said they expected the contractor to begin work as early as Friday night. Golden Triangle, which submitted the lowest responsible bid out of nine contractors that wanted the work, declined to comment.

Advertisement

Preliminary work is expected to begin immediately but construction of the wall likely won't start for several weeks while the contractor obtains precast concrete panels and fabricated steel rods.

The project will replace a previous retaining wall that gave way during the landslide. Ja­son Zang, PennDOT’s act­ing as­sis­tant di­rec­tor for con­struc­tion, said the col­lapse oc­curred in a 200-foot area where the bedrock is about 50 feet lower than it is under neighboring parts of the highway.

In addition, lower-quality fill used when the highway was built in the 1930s didn’t provide proper drainage, he said. Record amounts of rainfall that began in February caused the landslide, officials believe.

With the new design, crews will drill holes 4 feet in diameter and fill them with concrete to create pylons to support the wall. In addition, steel rods will be pounded horizontally into bedrock to anchor it.

An aerial view of the Route 30 landslide in East Pittsburgh, as seen on Tuesday April 10, 2018. Three lanes of Route 30 collapsed.
Ed Blazina
Feds reimburse PennDOT nearly $10 million for Route 30 collapse

When the wall is finished, crews will put in about 40,000 cubic yards of fill — 10,000 cubic yards of granular material and 30,000 cubic yards of durable rock — to allow better drainage.

The last step will be rebuilding the highway, which should take about two weeks. The contractor will lay a new subsurface and rebuild the collapsed area as well as 100 feet or more on each end of the collapse to restore the surface.

The winning bid for the project was within PennDOT’s $5 million to $7 million projection. The state will ask the Federal Transportation Administration for emergency funding to pay for that work as well as several million dollars more that it has spent on emergency housing for 31 displaced residents, hill stabilization and designing the wall and road repairs.

Ten residents will need new permanent housing but 21 should be able to return to their apartments when the wall is finished in mid-June. A house about a third of the way up the hillside on Beech Street Extension and owned by Chris Morgan was demolished Friday because slide damage made it uninhabitable.

The displaced residents have been staying with relatives or in hotels at state expense since the slide.

PennDOT and a consultant had been monitoring the section of Route 30 that eventually collapsed for several weeks because it was buckling and lanes of traffic had been reduced. It was closed completely the day before the collapse and residents were evacuated the next morning with no injuries.

Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.

First Published: April 20, 2018, 7:30 p.m.
Updated: April 20, 2018, 7:30 p.m.

RELATED
This view shows a portion of Route 30 that collapsed and slid down a hillside, forcing the evacuation of dozens of residents living along Electric Avenue in East Pittsburgh. This photo was taken from the Chalfant neighborhood.
Shelly Bradbury and Ed Blazina
Unstable ground delaying effort to plan for Route 30 rebuilding
Demolition crews begin tearing down a house near Route 30 in the area where a portion of the highway collapsed on April 7. The house was being razed to make way for a new retaining wall.
Pittsburgh Post-Gazette
Crews demolishing house near Route 30 landslide
Workers clear the section of Route 30 in East Pittsburgh that was destroyed April 7 by a landslide in East Pittsburgh.
Ed Blazina
View from Route 30 — what's left of it — shows enormity of collapse, landslide
An aerial view of the Route 30 landslide in East Pittsburgh. Three lanes have collapsed.
Don Hopey
Blame geology and weather: Landslides a common annoyance in Western Pennsylvania
Cheryl Moon-Sirianni, Pennsylvania Department of Transportation District Executive, and her associate Jason Zang, Acting District Assistant Executive for Construction, announce a wall project in response to the landslide and displacement along Route 30 during a press conference Tuesday April, 17, 2018, in Bridgeville. Companies are asked to have their bids in for the wall by this Friday, April 20, 2018. PennDot hopes to have the wall fully constructed by mid-June.
Ed Blazina
PennDOT planning to award contract for Route 30 retaining wall, road replacement
SHOW COMMENTS (0)  
Join the Conversation
Commenting policy | How to Report Abuse
If you would like your comment to be considered for a published letter to the editor, please send it to letters@post-gazette.com. Letters must be under 250 words and may be edited for length and clarity.
Partners
Advertisement
Pittsburgh Steelers head coach Mike Tomlin talks to quarterback Russell Wilson (3) during an NFL football game, Sunday, Oct. 20, 2024, in Pittsburgh.
1
sports
Joe Starkey: Steelers staging the saddest quarterback derby there ever was
A member of civil defense canine unit searches for Sudiksha Konanki, a university student from the U.S. who disappeared on a beach in Punta Cana, Dominican Republic, Monday, March. 10, 2025. (AP Photo/Francesco Spotorno)
2
local
‘Person of interest’ named in disappearance of Pitt student Sudiksha Konanki in Dominican Republic
Pittsburgh Steelers head coach Mike Tomlin walks the sidelines during the first half of an NFL football game against the Kansas City Chiefs, Wednesday, Dec. 25, 2024, in Pittsburgh.
3
sports
Gerry Dulac's Steelers chat transcript: 03.12.25
Larry Ogunjobi swarms Aaron Rodgers during the Steelers’ victory against the Jets in October.
4
sports
Former Steelers Larry Ogunjobi, Van Jefferson land elsewhere in free agency
New York Jets quarterback Aaron Rodgers (8) looks on next to head coach Robert Saleh during an NFL football game against the New York Giants, Saturday, Aug. 26, 2023 in East Rutherford, N.J. Jets won 32-24.
5
sports
Free agency waiting game between Steelers, Aaron Rodgers presses on
A contractor is on a lift, to the right, as the back of a house is demolished first, below the landslide on Route 30 and near Electric Avenue on Friday in North Braddock. The demolition crew was trying to spare the warehouse below from the damaging debris.  (Darrell Sapp/Post-Gazette)
Debris lays along the side and below the house as it is demolished, below the landslide on Route 30 and near Electric Avenue, Friday morning, in North Braddock. The demolition crew was trying to save the warehouse below from the damaging debris.  (Darrell Sapp/Post-Gazette)
Debris lays along the side and below the house as it is demolished, below the landslide on Route 30 and near Electric Avenue.  (Darrell Sapp/Post-Gazette)
Darrell Sapp/Post-Gazette
Advertisement
LATEST news
Advertisement
TOP
Email a Story