The Liberty Bridge will close this weekend for continued reconstruction work on the span
1
MORE

TRAFFIC: Clemente Bridge closing at 2 p.m. for Pirates game; Liberty Bridge closing tonight

Steve Mellon/Post-Gazette

TRAFFIC: Clemente Bridge closing at 2 p.m. for Pirates game; Liberty Bridge closing tonight

The Liberty Bridge is scheduled to close this weekend for continued reconstruction work, starting Friday night at 8 p.m.

The bridge will reopen around 5 a.m. Monday. Crews will conduct barrier removal, line eradication and painting, lane control system adjustments, and other construction activities. 

The outbound Liberty Tunnel and McArdle Roadway will remain open all weekend. A single-lane will remain open in the inbound Liberty Tunnel.

Advertisement

All other traffic will be detoured during the closure.

Other traffic restrictions:

Route 19 ramp closure — The southbound Route 19 (West Liberty Avenue) ramp to southbound Route 51 (Saw Mill Run Boulevard) is closed through 5 a.m. Monday, June 19 for concrete patching, spall repairs, ADA curb cut ramp installation, pavement overlay, and drainage improvements. Detours will be posted.

Route 51 — Northbound over Route 19 (West Liberty Avenue) closed around-the-clock through June 22 for bridge work. Detour is northbound traffic to ramp toward Truck 19 south/Dormont - 579 Downtown/South Side. Motorists continuing to northbound Route 51, will cross over Route 19 and take the ramp back to northbound Route 51.

Advertisement

There are two lanes open to northbound Route 51 on the detour route. Also, motorists will be able to turn in each direction at the intersection with Route 19.

Also, one lane is closed along southbound Route 51 (Saw Mill Run Boulevard) between Bausman Street and Edgebrook Avenue weekdays from 9 a.m. to 3 p.m. through June 23. Crews from Power Contracting Company will conduct ITS pole and electrical work.

Parkway North — New traffic configuration along the Parkway North south of the McKnight Road interchange as part of a $87 million rehabilitation project:

▪ Two southbound lanes will continue to shift from the HOV lanes back into mainline I-279 near the Venture Street interchange.

▪ A single-lane of the closed portion of the High Occupancy Vehicle (HOV) lanes will reopen to traffic:

▪ Motorists in the left-hand lane approaching the shift to mainline I-279 at Venture Street may choose to stay in the newly reopened HOV lane.

▪ Motorists using the HOV lane will only be able to use the slip ramp to southbound I-279 south of the I-579/Veterans Bridge exit. No access to Anderson Street or Stadium Drive will be permitted.

▪ Additionally, motorists using the HOV lane will not have access to the North 28/East Street (Exit 2B) or South I-579/Veterans Bridge (Exit 2A) exits.

▪ The Bedford Avenue HOV lane will only open prior to Penguin’s home games.

▪ No HOV access in the northbound direction will occur.

▪ The ramp from North Canal Street to southbound I-279 will be reduced to a single-lane to accommodate reconstruction work. The ramp will remain open to traffic but will be placed in a stop condition at I-279.

▪ Mainline I-279 between the I-579/Veterans Bridge off-ramp and Anderson Street will be reduced to a single-lane.

The 8.5-mile work zone from Camp Horne Road to the McKnight Road interchange will remain unchanged.

Russellton-Dorseyville Bridge, West Deer — Bridge replacement work has closed Russellton-Dorseyville Road between Saxonburg Boulevard and East Union Road around-the-clock through late August. Detours will be posted.

Route 65, Leetsdale — Lane restrictions between Cross Street and Broad Street weekdays through June 16 for removal of the Leet Street Bridge:

▪ Southbound from 9 a.m. to 5 p.m.; northbound from 7 a.m. to 3 p.m.

The bridge has been closed to vehicular traffic since October 2013.

Western Avenue, North Side — Single-lane restrictions between Fulton Street and the West End Bridge weekdays from 7 p.m. to 2 p.m. the next day, through late July.

Roberto Clemente Bridge (Sixth Street Bridge) — The bridge will be closed on some Fridays to accommodate Pirates games:

▪ Friday, Sept. 22 – On game days, the bridge will be closed to vehicular traffic starting at 2 p.m., and it will reopen to vehicular traffic one hour after the end of each game.

• Saturdays, Sundays and Holidays – On game days, the bridge will be closed to vehicular traffic at various times requested by the Pirates, and it will reopen to vehicular traffic one hour after the end of each game.

• Sidewalks on the Roberto Clemente and Rachel Carson bridges will be open for all games.

Liberty Interchange (Routes 51 and 19) — Overnight closures as part of a $4.3 million improvement project of the south portal of the Liberty Tunnel at Route 51 (Saw Mill Run Boulevard) and Route 19 (West Liberty Avenue) interchange. Work will occur weeknights from 8 p.m. to 5 a.m. and on weekends from 8 p.m. Friday night continuously through 5 a.m. Monday morning, through July, in the following locations:

▪ Route 51 between Bausman Street and Crane Avenue

▪ Route 19 between Pioneer Avenue and the Liberty Tunnel

Wabash Tunnel — Inbound tunnel will be open at 5 a.m. weekdays and just after 2:30 p.m. for outbound motorists to help ease congestion caused by the Liberty Bridge construction projects. HOV vehicle occupancy restrictions will be lifted during the extended hours of operation.

Route 65/Ohio River Boulevard -— PennDOT has announced long-term lane restrictions on northbound Route 65/Ohio River Boulevard as part of a $25.3 million improvement project:

▪ A lane will be closed from Fort Duquesne Bridge to the West End Bridge and from West End Bridge to the McKees Rocks Bridge. Around-the-clock closure lasts through Sept. 7. Two 11-foot lanes will be maintained. Work will include concrete patching, an asphalt overlay, bridge reconstruction, base repairs, drainage and guide rail updates, new signs, retaining wall repairs and pavement-marking installation.

▪ Single lane overnight in both directions between 7 p.m. and 6 a.m. Tuesday through Thursday nights for milling and resurfacing activities.

Interstate 376 — Long-term lane restrictions on westbound Interstate 376 in Findlay between Business Loop 376 West/Moon (Exit 57) and the Airport/East PA Turnpike 576 (Exit 53) interchanges, will be reduced to two 11 foot-wide lanes. The new configuration will be maintained through mid-November as crews reconstruct the concrete roadway, and conduct bridge and ramp repairs.

▪ Also, westbound I-376 off-ramp to Business Loop 376 West/Moon (Exit 57) will be reduced to a single-lane lane through mid-November. The ramp will remain open as crews conduct roadway reconstruction work.

Other restrictions in that area include:

▪ Intermittent single-lane restrictions eastbound (inbound) between Beaver County line and the McClaren Road (Exit 56) interchange, weekdays from 7 a.m. to 3 p.m. westbound and 9 a.m. to 5 p.m. eastbound as crews from Swank Construction begin median crossover work as part of the $66.3 million reconstruction project.

Route 51/Saw Mill Run Boulevard — Northbound over Route 19 (West Liberty Avenue) closed around-the-clock through June 22. Crews from Gulisek Construction will conducting bridge preservation work. Detours will be posted:

▪ Northbound traffic will take the ramp toward Truck 19 south/Dormont - 579 Downtown/South Side

▪ Motorists continuing to northbound Route 51, will cross over Route 19 and take the ramp back to northbound Route 51

Two lanes of traffic will be accommodated to northbound Route 51 on the detour route. Also, motorists will be able to turn in each direction at the intersection with Route 19.

Also, one lane is closed along southbound Route 51 (Saw Mill Run Boulevard) between Bausman Street and Edgebrook Avenue weekdays from 9 a.m. to 3 p.m. through June 23. Crews from Power Contracting Company will conduct ITS pole and electrical work.

McClaren Road, Findlay — McClaren Road closed between Garden Lane and Mustang Drive through mid-November so crews from Golden Triangle Construction to conduct road reconstruction and bridge repairs.

Interstate 79, Butler County — Work underway on a $16.7 million paving project. Southbound lane restrictions in the area of Jackson and Cranberry through mid-June.

• Also lane closures in each direction during off-peak hours, between 6 p.m. and 6 a.m. daily with two exceptions. On Fridays, work in the northbound lanes will start at 9 p.m. and on Sundays work in the southbound lanes will be start at 9 p.m., through October.

Braddock Avenue/Hamilton Avenue, Homewood — Traffic signal replacement project will cause lane closures and short-term detours through June, from 9 a.m. to 3 p.m. daily.

Warrendale Bayne Road, Marshall — Lane closures as part of a $1.28 million road improvement project will last through October:

• Intermittent single-lane alternating traffic will occur as needed on weekdays from 9 a.m. to 3 p.m. and weeknights from 7 p.m. to 6 a.m. as crews conduct the work at intersection with Brush Creek Road/southbound I-79 on-ramp, and at intersection with Innovation Drive. A single lane in each direction will be maintained during peak travel times. The southbound I-79 ramp will remain open during construction. Crews from Frank J. Zottola Construction, Inc. will conduct roadway widening, milling and paving, drainage improvements, sidewalk improvements, signal upgrades and pavement marking installation.

Glenwood Bridge — The next phase of the $17 million Glenwood Bridge interchange rehabilitation project involves the following restrictions:

▪ Around-the-clock single-lane restriction through November in each direction of Route 885 for bridge work over the northbound Route 837 ramp to southbound Route 885. One lane of Route 885 will remain open in each direction.

▪ Southbound Route 837 ramp to northbound Route 885 will be closed to traffic around-the-clock through late July. Traffic will be detoured.

▪ Around-the-clock single-lane closure on northbound Route 885 in the area of the closed southbound Route 837 ramp to northbound Route 885, through November. One lane will remain open on northbound Route 885.

▪ Route 837 traffic to southbound Route 885 will detoured at the Hot Metal Bridge, but southbound Route 837 traffic may continue to Becks Run Road.

▪ Also, four weekend closures will occur. PennDOT says more information will be provided once the closures are scheduled.

Andy Warhol Bridge — Closed to vehicular and pedestrian traffic through November as part of $25.4 million rehabilitation project. The Rachel Carson Bridge (9th Street) will be used as a detour. The detour also will reroute about 350 Port Authority buses a day to Carson, according to the Port Authority. The detoured routes will be routes 1, 2, 4, 6, 7, 8, 11, 12, 13, 15, 16, 17 and the O5. The Carson Bridge is expected to be rehabbed in 2018 and the Clemente Bridge in 2020.

Clifton Road, Bethel Park — Gas line work will restrict the road to single-lane, alternating traffic between Kings School Road and Brush Run Road from 9 a.m. to 3 p.m. weekdays through Aug. 15. Also single-lane alternating traffic on Irishtown Road/Braun Road during the same period.

Liberty Bridge/Tunnels — Weekday lane restrictions on the bridge as crews continue to work on bridge reconstruction and steel repairs:

▪ Two inbound lanes and one outbound open from 5 a.m. to 2 p.m.; one inbound and two outbound lanes from 2 to 7 p.m.; and one lane in each direction from 7 p.m. to 5 a.m.

▪ Liberty Bridge ramps to and from the Boulevard of the Allies will remain closed through June.

▪ Also, the Boulevard of the Allies between Grant Street and the Liberty Bridge is closed through June for deck reconstruction, steel repairs and painting operations.

Detours are posted.

East Pennview Street, Shaler — Closed for bridge replacement. Pine Creek Bridge No. 11, about a quarter mile west of the intersection of Pennview and Route 8, through the spring.

I-376 cashless tolling — The Pennsylvania Turnpike Commission has begun using cashless tolling on a stretch of Interstate 376 known as the Beaver Valley Expressway.

The 16.5-mile tolled portion of Interstate 376 between Chippewa and New Castle will have no toll collectors. Motorists who don’t have an E-ZPass transponder will have a photograph taken of their license plate and receive a bill once a month similar to a credit card payment with 20 days to pay.

The billing cycle will start the first time a driver goes through the toll booth without a transponder and a bill will be issued 30 days later. Users of E-ZPass will have fares deducted from their account as usual.

Cavasina Drive, Canonsburg — Northbound lane closure at the intersection with Route 1009/Morganza Road and Route 1025/Weavertown Road in Canonsburg/North Strabane through Sept. 14 to allow crews to perform intersection widening and traffic signal upgrades.

Travel tools:

Pa. Turnpike — For conditions on the Pennsylvania Turnpike, check out www.paturnpike.com and check the “Current Alerts” ticker at the top for restrictions.

511PAConnect — Provides information updates to motorists via automated phone or text message in the event of a long-term road closure due to accidents on the Pennsylvania Turnpike or other state roadways.

First Published: June 16, 2017, 10:36 a.m.
Updated: June 16, 2017, 4:51 p.m.

RELATED
SHOW COMMENTS (0)  
Join the Conversation
Commenting policy | How to Report Abuse
If you would like your comment to be considered for a published letter to the editor, please send it to letters@post-gazette.com. Letters must be under 250 words and may be edited for length and clarity.
Partners
Advertisement
Around 450,000 Pennsylvanians enrolled in Affordable Care Act health insurance plans this year, but credits expire at the end of 2025, which will mean dramatic premium hikes in 2026 unless Congress votes for an extension.
1
business
Crunch time: 450K Pennsylvanians with Obamacare could see dramatic spikes in health care costs
Bill Sunseri, president of Pennsylvania Macaroni Co., stands in his family’s store on Jan. 6 in the Strip District.
2
life
Pennsylvania Macaroni Co. has a new full owner at the helm
Meredith Miller of Upper St. Clair.
3
news
Woman who died in Upper St. Clair fire remembered as devoted churchgoer and teacher
SEATTLE, WASHINGTON - JANUARY 25: Joey Daccord #35 of the Seattle Kraken clears the puck against Evgeni Malkin #71 of the Pittsburgh Penguins during the first period at Climate Pledge Arena on January 25, 2025 in Seattle, Washington. (Photo by Steph Chambers/Getty Images)
4
sports
Snake-bitten Penguins lose Evgeni Malkin to injury in defeat to Kraken
Steelers coach Mike Tomlin, middle, sits between assistant secondary coach Anthony Midget, left, and secondary coach Grady Brown, right, before taking on the Eagles Dec. 15, 2024, at Lincoln Financial Field in Philadelphia.
5
sports
How does Steelers coaching staff compare to NFL's best? Lean, broadly defined and working double time
The Liberty Bridge will close this weekend for continued reconstruction work on the span  (Steve Mellon/Post-Gazette)
Steve Mellon/Post-Gazette
Advertisement
LATEST news
Advertisement
TOP
Email a Story