It’s the kind of job that requires ice in the veins.
The task is to demolish a massive seven-story cold storage warehouse built like a bomb shelter with a 12-inch-thick concrete outer skin and a 16-inch-thick inner skin.
And to do so without crushing the tiny red brick bar called Lucky’s tucked right up against its east side.
“It’s not for the faint of heart,” developer Matt Cassin conceded.
Acram Group, Mr. Cassin’s company, and Continental Construction and Demolition, the contractor it hired, have been going at it since late fall, chipping away at the brawny building.
At this point, the old warehouse dating to 1930 looks as if it’s part of a war zone, with a gaping hole in its middle and rubble surrounding it.
Read More
But the 330,000-square-foot New Federal Cold Storage Building, perhaps best known for the giant smiling fish sign that served as a beacon into the Strip for years, is proving to be a formidable foe.
After about six months of work, three sides are still standing, although much of the interior has been gutted.
“It was built to last,” said Chris Deppoliti, Acram head of asset and property management.
For years, the warehouse was used by Robert Wholey & Co., whose popular Strip market is just a couple of blocks away.
It took a force of 500 people, working three shifts daily, a total of 13 days to build the 100-foot-high outer wall, according to an article in the Pittsburgh Press. It required 7,000 cubic yards of concrete.
The building was believed to be the first in Pittsburgh to use a “slip form” construction method. Besides the beefy walls, the warehouse featured 9½-inch-thick floors.

At this point, Mr. Deppoliti hopes to be “substantially complete” with the demolition by mid-July. That’s about a month later than he first thought.
“Just the complexity of the project,” he explained. “It has taken a bit longer.”
Given little Lucky’s and other buildings surrounding the site, including Facebook’s Pittsburgh headquarters, this isn’t the kind of job that calls for a few sticks of dynamite and a wrecking ball.
Instead, most of the work has been done by an excavator, picking and plodding its way through two feet of concrete and another foot of cork — used to keep out heat — in a building that literally was meant to be a giant ice box.
“It’s a very substantial demolition job that has its complexities,” Mr. Deppoliti said. “We understood that going in.”
Some of those challenges have included protecting neighbors like Lucky’s from the fallout and trying to keep the work within the building footprint to prevent traffic disruptions.
All of six inches separates the three-story Lucky’s and the cold storage warehouse that looms over it.
Cement dust covers the slanted roof and part of the brick on the little bar’s back side. One slip up could send thick chunks of concrete tumbling onto the drinking spot.
Given that, it seems appropriate that a shamrock-shaped sign hangs over Lucky’s entrance on Penn Avenue. A sign next to the door states that smoking is allowed, perhaps to calm any jitters over the work taking place next door.
A plaque attached to the facade reads, “On this site in 1897, nothing happened.” It’s likely that all involved are hoping the same can be said 125 years later.
Acram, Mr. Deppoliti noted, is taking precautions to ensure that will be the case.
It is saving the work next to Lucky’s for last. All of the concrete will be removed by hand more in line with a surgeon’s touch rather than blunt force.
Right now, there is no visible damage to the bar, the closest neighbor. The Lucky’s owner could not be reached for comment. A woman who answered the phone at the bar said the demolition so far hasn’t been an issue.
“They’ve stayed open,” Mr. Deppoliti said. “We’re working very closely with them. They’ve been great to work with.”
The cold storage building also is close to the Allegheny County medical examiner’s office, the Facebook headquarters, and a Homewood Suites hotel. Amie Downs, county spokeswoman, said the work hasn’t caused any disruptions for the medical examiner’s office.
Pamela Austin, president and board chair of the Strip District Neighbors community group, said sensors have been installed near the demolition to monitor vibrations.
She added that there have been some unexpected road closures near the site, but that they haven’t been tied to the demolition work itself.
While Acram has razed buildings in New York City in the past, this is the first time it has tackled a cold storage warehouse.
Mr. Deppoliti acknowledged that it was probably one of the “more substantial” demolitions the company has undertaken. The work will cost about $2 million.
Once the building has been leveled, another big one will rise in its place.
Acram is planning an office complex featuring four “mini-towers,” with the tallest facing Downtown being 23 stories. The smallest one facing the Strip will be 19 and the other two will be 21.
It will be the biggest structure in the Strip by far.
And though it’s not meant to be a nod to the past, the building will deliver air conditioning through pipes in the ceiling rather than through a conventional forced air system using ducts. It’s designed to help prevent the spread of germs and viruses in the age of COVID.
“It’s a great project. We’re super excited about the development project in total and really believe we’re going to deliver a best-in-class trophy asset to Pittsburgh,” Mr. Deppoliti said.
But first, there’s still some work to do in taking down an old one.
Mark Belko: mbelko@post-gazette.com or 412-263-1262.