Tuesday, April 22, 2025, 1:34PM |  54°
MENU
Advertisement
The ticketing level of the Pittsburgh International Airport Landside Terminal on Tuesday, March 23, 2021 in Findlay.
6
MORE

At the gate: Airlines authorize more spending on airport modernization as cost increases

Andrew Rush/Post-Gazette

At the gate: Airlines authorize more spending on airport modernization as cost increases

After a year of stalled construction due to the pandemic, airlines have cleared for takeoff more spending on a Pittsburgh International Airport modernization project whose cost has jumped to nearly $1.4 billion, an increase of almost $300 million.

Carriers last week authorized $182 million in funding for site preparation work for the project, which includes the construction of a new terminal for ticketing, security and baggage claim.

The decision represents the resumption of construction after a yearlong delay caused by the COVID-19 pandemic, according to the Allegheny County Airport Authority, which oversees Pittsburgh International.

Advertisement

In announcing the authorization, the authority stated that the budget for the project is now set at $1.39 billion. That’s an increase of $290 million, or 26.4%, over the original estimate of $1.1 billion.

Pittsburgh International Airport has struck a deal with the airlines on a new two-year lease agreement.
Mark Belko
New 2-year lease with airlines includes more design spending for $1.1 billion Pittsburgh airport modernization

The authority attributed the increase to “design evolutions” authorized by the airlines and costs associated with the delay.

Airlines would shoulder the cost of the construction through rates and charges paid to the authority to operate at the Findlay airport, although there likely would be some federal or state funding involved.

Paul Hoback, the authority’s chief development officer, said he’s not expecting public funding to be significant.

Advertisement

“The airlines are the primary backers of the debt associated with this work,” he said.

The new spending has won the support of the airport’s two largest carriers, American and Southwest, as well as others.

“The PIT team has been a fantastic partner throughout this entire process,” Patrick Bowes, manager of corporate real estate for American and chair of the airport and airline affairs committee, said in a statement. “While we still need to finalize a long-term agreement, the fact that there is airline support of the terminal modernization program during what has been a very challenging time for our industry and the entire economy is a testament to the great work the team has done — and the merits of the project itself.”

“Southwest is in support of the next step towards the terminal modernization plan, and we are looking forward to working collaboratively with the Allegheny County Airport Authority to ensure a successful program,” added Brian Parrish, a Southwest spokesman.

Design concept for terminal modernization program at Pittsburgh International Airport
Mark Belko
Facing headwinds? Change in airport’s credit outlook could complicate plans for $1.1B modernization

All nine “signatory” airlines, meaning those that operate under an airport lease agreement, backed the new spending, Mr. Hoback said.

Besides American and Southwest, they are Delta, United, Spirit, Allegiant, JetBlue, Alaska and British Airways, which currently is not flying from the airport because of the pandemic.

The additional spending comes at a time when the airport is starting to show signs of life after watching traffic plummet to next to nothing because of COVID-19. 

On March 11, 7,465 travelers passed through the airport’s security checkpoint. That’s the second-best total since March 15, 2020. The highest was Dec. 27, when 7,583 passengers cleared the checkpoint. On an average day pre-COVID, about 15,000 people went through security.

And last week, the airport experienced its busiest week since the pandemic started, with nearly 42,000 people passing through the checkpoint.

Though COVID-19 had held up construction, the carriers had authorized $150 million in design spending last year in approving a new two-year lease with the authority.

The new spending “officially clears the way for construction to begin on the first airport terminal in the U.S. to open post-pandemic, designed and constructed with the highest public health standards in mind,” authority CEO Christina Cassotis said in the airport’s Blue Sky newsletter.

With the authorization, the authority will be able to go ahead with contracts for structural steel and concrete decks, foundations and underground utilities this spring. Money also was allocated for additional design work and project management.

Furthermore, the authority last week gave the go-ahead to start work on more than $19 million in contracts related to early site preparation that had been scheduled to advance last April. The $19 million is included in the $182 million the airlines authorized.

With the new spending approved, site work should start as early as next month.

Fencing will be going up. Crews will be tearing up concrete on the west ramp between the airside building’s C and D concourses to make way for the new landside terminal, which will be tucked between those two arms. 

Some of the new spending will be to erect the steel skeleton of the new building.

Nonetheless, the building envelope itself, interior construction, and roofing as well as other aspects of the modernization, including a 3,300-space parking garage and new roadways, are still contingent on the authority reaching a long-term lease deal with the airlines and floating the revenue bonds needed to pay for the project.

Mr. Hoback said the authority is hoping to have the new lease agreements in place sometime this summer. It then would work with the airlines on the right time to go to the bond market, perhaps as early as this fall.

“We acknowledge that there is still some work to do to get that long-term agreement in place,” he noted. 

If all goes as planned, the authority hopes to conclude construction by mid-2024 and open the new terminal in early 2025.

Mr. Hoback said he is confident there will be no other increases in the $1.39 billion budget for the modernization.

The new terminal would replace the existing landside building, which would be demolished or repurposed. The airside building would continue to be used to get on and off planes. The tram that now takes travelers between the landside and airside buildings would be eliminated.

While some, like midfield terminal architect Tasso Katselas and former state Rep. Mike Turzai, have questioned the need for the project, Mr. Hoback said it will improve the experience for travelers and stabilize operations and maintenance costs.

The midfield terminal, a former hub for US Airways, was built for a different time, a different function and a different business model than today, he maintained.

“It’s always been about right sizing the airport,” he said of the new project.

Mark Belko: mbelko@post-gazette.com or 412-263-1262.

This story was updated at 5:50 p.m. on March 23.

First Published: March 23, 2021, 2:40 p.m.

RELATED
A conceptual design for the terminal modernization at the Pittsburgh International Airport
Mark Belko
Airport $1.1 billion modernization hits turbulence — COVID-19
Design Concept for Terminal Modernization Program at Pittsburgh International Airport Revealed at Annual State of the Airport Event International design team draws inspiration from nature, technology, and community of western Pennsylvania; New terminal to combine landside and airside operations into one modern, adaptable facility PITTSBURGH — As part of a special board meeting and the annual State of the Airport event on Wednesday, Feb. 20, the Allegheny County Airport Authority Board of Directors approved a visionary concept design for the Terminal Modernization Program at Pittsburgh International Airport. The concept design for the new terminal to be built adjacent to the current Airside facility between Concourses C and D and scheduled to open in 2023, was unveiled to airport employees and the public on Wednesday.  Provided
Mark Belko
Site work for $1.1 billion airport modernization to start in April
A traveler walks along the pedestrian walkway at the Pittsburgh International Airport on Thursday, Nov. 19, 2020, in Findlay.
Mark Belko
Pandemic blues: Airlines will see rates climb despite Pittsburgh International Airport budget cuts
SHOW COMMENTS (23)  
Join the Conversation
Commenting policy | How to Report Abuse
If you would like your comment to be considered for a published letter to the editor, please send it to letters@post-gazette.com. Letters must be under 250 words and may be edited for length and clarity.
Partners
Advertisement
Dylan Sampson (#RB26) of Tennessee, Ashton Jeanty (#RB15) of Boise State and Woody Marks (#RB21) of USC participate look on during the NFL Scouting Combine at Lucas Oil Stadium on Saturday, March 1, 2025, in Indianapolis.
1
sports
NFL draft analysis: Christopher Carter’s Round 1 prospect rankings and Steelers priority targets
People flock to the Benedum Center for the Performing Arts to see Bob Dylan during his Rough and Rowdy Ways Tour in Pittsburgh on April 21, 2025.
2
a&e
Review: Bob Dylan show is a piece of Rough and Rowdy cabaret at the Benedum
A new training program that launched last month from an RIDC site in Hazelwood, Mill 19, pictured here, helps women learn computer-assisted design and build skills to hopefully market to a variety of employers.
3
business
Made in America is back, but Made in Pittsburgh is an open question
 Brandi Fisher, President of the Alliance for Police Accountability, holds up a copy of a mailer that circulated last last week against Mayor Ed Gainey's re-election campaign. Supporters of Mr. Gainey have decried the ad as racist and misleading.
4
news
Gainey supporters decry mailer advertisement in support of O'Connor
Pope Francis' body is laid out in state inside his private chapel Monday, April 21, 2025, at the Vatican.
5
news
Pope Francis’ funeral to be held Saturday, with public viewing starting Wednesday
The ticketing level of the Pittsburgh International Airport Landside Terminal on Tuesday, March 23, 2021 in Findlay.  (Andrew Rush/Post-Gazette)
Design concept for the Terminal Modernization Program at Pittsburgh International Airport. The new terminal would combine landside and airside operations into one modern, adaptable facility.  (Provided)
Long-term and short-term parking lots at Pittsburgh International Airport outside the Landside Terminal on Tuesday, March 23, 2021, in Findlay.  (Andrew Rush/Post-Gazette)
Design concept as part of the Pittsburgh International Airport modernization project whose cost has jumped to nearly $1.4 billion, an increase of almost $300 million.  (Provided)
Passengers in the baggage claim area of the Pittsburgh International Airport Landside Terminal on Tuesday, March 23, 2021, in Findlay  (Andrew Rush/Post-Gazette)
Passengers in the baggage claim area of the Pittsburgh International Airport Landside Terminal on Tuesday, March 23, 2021, in Findlay.  (Andrew Rush/Post-Gazette)
Andrew Rush/Post-Gazette
Advertisement
LATEST business
Advertisement
TOP
Email a Story